NO WORK will
be done
Labor Days
Sept 2nd Friday to Sept 6th Tuesday

September 1, 2016 ____
San Bernardino, California
The California Department of Transportation (Caltrans) District 8 has begun work on three
separate projects on State Route 330
(SR 330).
The projects will
install new guardrail in nine locations, reline and repair eleven existing
culverts and repave the route between State
Route 210 (SR 210) and Running Springs.
Traffic control, or
flagging, will be necessary during all three projects, Monday through Friday
between 7:00 A.M. and 4:00 P.M. Motorists are advised that major delays are anticipated
during work hours.
Use SR 18 or SR 38 to avoid
the work.
CALTRANS Work Schedules
are:
PROJECT
|
WORK SCHEDULE/
LANE CLOSURES
|
START DATE
|
COMPLETION
DATE
|
Midwest Guardrail Systems
Guardrail Project
|
Mon -Thurs
8:00 a.m. to 5:00 p.m.
Fri 8:00 a.m. – 4:00 p.m.
|
Mid-August
|
End of October 2016
|
Cal-Mex Engineering, Inc.
Paving Project
|
Mon -Thurs
8:00 a.m. to 5:00 p.m.
Fri 8:00 a.m. – 4:00 p.m
|
Mid-August
|
Expected to complete by end of 2016
|
Dream Builders
Culvert Project
|
Monday through Thursday (shoulder
closures only on Fridays)
8:00 a.m. to 3:00 p.m.
|
September 7 (tentative)
|
November 2016
|
Advisory signs are
posted in advance of the work zones.
Please reduce your speed
when you encounter flaggers or work crews.
The California Highway Patrol will be on site
to ensure the safety of
the workers and motoring public.
Know before you go!
To stay on top of
roadwork in the Inland Empire go to www.caltrans8.info
and sign up for commuter
alerts.
View traffic conditions
at http://quickmap.dot.ca.gov